Project Overview
US 87 bridge replacement over the Guadalupe River and relief including bridge approaches and reconfiguration of the intersection of US 87 and US 183.
Location: Cuero, TX Customer: TxDOT Engineer: TxDOT Contract Amount: $15.7MHighlights
- Constructed new bridge structure and approaches over the Guadalupe River.
- Successfully reconstructed the busy / dangerous intersection of US 183 and US 87
- Project completed on time despite project control issues and multiple grades revisions required to make US 87 approaches tie in to the new bridge structure.