Project Overview
Reconstruction of West Klein Rd between FM 725 and South Walnut including improved drainage and a new bridge.
Location: New Braunfels Customer: City of New Braunfels Engineer: Pape Dawson Contract Amount: $12.9 millionHighlights
- Constructed new bridge structure, improved drainage and two lanes of roadway in four months.
- Installed temporary waterline above ground through street crossings without altering existing conditions.
- Navigated multiple utility delays and conflicts without negatively impacting project performance.
- Project is 6 months ahead of schedule. (to date)